Community Campus Demolition Updates
Demolition work (outlined in blue on the map) is expected to be completed by the end of April 2024.
Demolition Schedule (Subject to change):
Skate Park Demolition: January 2024 - February 2024
Track Demolition: January 2024 - February 2024
Aquatic Center Demolition: January 2024 - February 2024
Old Middle School Demolition: February 2024 - March 2024