Community Campus Demolition Updates

Site Diagram

Demolition work (outlined in blue on the map) is expected to be completed by the end of April 2024.

 

Demolition Schedule (Subject to change): 

Skate Park Demolition: January 2024 - February 2024

Track Demolition: January 2024 - February 2024

Aquatic Center Demolition: January 2024 - February 2024

Old Middle School Demolition: February 2024 - March 2024