Bull Run Supply Pump Station - Pump & Pump Can Procurement

Bid/RFP Status: 
Open - accepting bids and proposals
Bid/RFP Due Date: 
Tuesday, November 26, 2024 - 2:00pm
Bid/RFP Reference Number: 
RFP# SDWRP 11-24

BID/RFP Due Date: Tuesday, November 26, 2024, at 2:00 pm

 

BID/RFP Reference Number: RFP # SDWRP 11-24

The City of Sandy desires to procure two (2) vertical turbine pumps and four (4) vertical turbine pump cans that will be incorporated into their planned Bull Run Supply Pump Station. The four pump cans will be installed by the Portland Water Bureau’s (PWB) construction contractor that is currently constructing the Water Bureau’s new water filtration facility located along Carpenter Lane in Multnomah County. The City and the PWB have an Inter-Governmental Agreement in place for the PWB’s contractor to complete the installation of the four pump cans, along with some other miscellaneous suction piping for the City at their proposed Bull Run Supply Pump Station located on PWB’s site. The two vertical turbine pumps will be installed by the City’s construction contractor during the full construction of the pump station project that is anticipated to go out for public bids in spring of 2025.

All questions about the meaning or intent of the Bidding Documents are to be submitted to Buyer and Engineer in writing and address the request to AJ Thorne, Assistant Public Works Director at ajthorne@ci.sandy.or.us and Eddie Kreipe, P.E. at eddie.kreipe@consoreng.com.

If you'd like to be added to the plan holders list, please email a request to Assistant Public Works Director AJ Thorne at: ajthorne@ci.sandy.or.us